Context & Problem
Previous launches had late PPAPs and post-launch issues. The organization needed a structured approach to gather and present PPAP evidence and ensure processes were stable before volume ramp.
Methodology & Frameworks
Process flow, FMEA, control plan aligned. MSA acceptable before capability. Cpk/Pp for key characteristics. Run-at-rate to verify no bottlenecks or quality issues at volume.
Implementation
A cross-functional team owned PPAP deliverables. FMEA and control plan were built early; MSA and capability were completed before run-at-rate. All documents were packaged for customer submission. A launch checklist ensured nothing was missed.
Outcomes
- On-time PPAP approval—customer accepted with no major findings.
- Zero launch escapes in the first 90 days of production.
- Repeatable checklist for future programs.
Lessons Learned
Start PPAP early; MSA and capability take time. Align FMEA, control plan, and process flow. Run-at-rate surfaces issues that bench trials miss. A single owner for PPAP coordination prevented dropped items.