PPAP & New Product Launch

New Product

PPAP per AIAG: flow, FMEA, control plan, MSA, capability, run-at-rate. On-time customer approval and zero launch escapes.

Executive Summary

A new product launch required customer approval and evidence of capable processes. This project delivered PPAP per AIAG: process flow, FMEA, control plan, MSA, capability studies, and run-at-rate. Outcomes: on-time PPAP approval, zero launch escapes, and a repeatable launch checklist.

  • On-time PPAP approval from customer
  • Zero launch escapes in first 90 days
  • Repeatable launch checklist for future programs

Context & Problem

Previous launches had late PPAPs and post-launch issues. The organization needed a structured approach to gather and present PPAP evidence and ensure processes were stable before volume ramp.

Methodology & Frameworks

Process flow, FMEA, control plan aligned. MSA acceptable before capability. Cpk/Pp for key characteristics. Run-at-rate to verify no bottlenecks or quality issues at volume.

Implementation

A cross-functional team owned PPAP deliverables. FMEA and control plan were built early; MSA and capability were completed before run-at-rate. All documents were packaged for customer submission. A launch checklist ensured nothing was missed.

Outcomes

Lessons Learned

Start PPAP early; MSA and capability take time. Align FMEA, control plan, and process flow. Run-at-rate surfaces issues that bench trials miss. A single owner for PPAP coordination prevented dropped items.